PEVELY — An evidence room holding more than 11,000 items, aging police vehicles and water facilities needing backup power were among the concerns brought before the Pevely Board of Aldermen during its November 16 meeting.
Department leaders presented spending requests for the upcoming budget, describing equipment failures, maintenance needs and preparations for emergencies. Aldermen questioned costs and replacement schedules, including whether a proposed purchase of six police vehicles should be spread across multiple years.
The board also approved an agreement for a no-cost assessment of wastewater treatment facilities. The larger department spending requests remained proposals during the meeting.
Police Seek Outside Help With More Than 11,000 Evidence Items
Police officials described a substantial undertaking in the department’s evidence room, where they said more than 11,000 pieces of evidence need to be inventoried and reviewed.
According to the presentation, the department inherited a backlog that includes items retained for decades. Staff must determine which items remain necessary for active cases, which can be returned to their owners and which may be destroyed with the appropriate authorization.
Police leaders said existing personnel cannot complete the work on their own while maintaining other responsibilities. They presented two options for outside assistance: approximately $46,000 for a team to complete the work in about one week, or approximately $44,000 for a smaller team working over roughly three months.
A department employee would serve as a liaison, helping connect evidence with case records and coordinate with prosecutors.
Officials tied the work to the department’s goal of obtaining accreditation by November 2028. They also emphasized the importance of properly accounting for evidence to protect criminal cases.
A separate proposal called for a secure storage container costing approximately $4,200. Police said it could accommodate larger evidence items and provide temporary storage during a future evidence-room renovation, which was discussed for 2028.
Six-Vehicle Proposal Prompts Questions About Replacement Schedule
The police department proposed acquiring six equipped Dodge Durangos at an outright purchase cost of roughly $460,000.
An alternative would spread payments over three years, with the city purchasing the vehicles for $1 each at the end of the lease. The presenter estimated that the difference between purchasing and leasing would be approximately $5,100, before accounting for trade-ins.
Police officials said newer vehicles would help reduce repair expenses by keeping more of the fleet under warranty. They described problems with older vehicles and cited instances in which warranty coverage had paid for significant repairs.
Aldermen questioned whether acquiring all six vehicles together would create another large replacement expense later. One suggested staggering purchases or leases in groups of two or three so the city could establish a more consistent annual replacement schedule.
The discussion also covered trade-in values, maintenance responsibilities and the cost of emergency equipment installed in the vehicles. No vehicle purchase or lease was approved during the presentation.
Cybercrime Partnership Would Cost $60,000 Annually
Police leadership also requested $60,000 annually for a partnership with the Jefferson County Sheriff’s Office’s cybercrime unit.
The chief said investigations increasingly involve cellphones, online activity, financial fraud and other digital evidence that require specialized equipment and training.
Establishing comparable capabilities within Pevely would be expensive, he told the board, estimating that a computer system alone could cost approximately $100,000 before staffing, training, software and ongoing maintenance.
The proposed partnership would give local investigators access to existing expertise and technology. The chief cited investigations involving suspected exploitation of minors and financial scams targeting older residents as examples of cases requiring that assistance.
Police also discussed a covered equipment trailer for emergency management and crime-scene response, with a base quote of approximately $4,000 before additional outfitting. Officials reported pursuing grants and other outside funding to help meet equipment needs.
Backup Power and Sewer Repairs Among Utility Priorities
Water department staff proposed backup generators at four locations, estimating a cost of approximately $100,000 per generator, or $400,000 for all four.
Staff identified Hunters Glen and the Industrial well location as priorities. They explained that Hunters Glen’s water supply operates separately and that the Industrial location helps supply Southern Heights, making backup power important during an outage.
The department also requested approximately $20,000 to expand chlorine-monitoring capabilities. Staff said the additional equipment would address anticipated Missouri Department of Natural Resources requirements.
Sewer requests included approximately $35,000 to replace deteriorating fencing at three locations and $35,000 for a backup pump at a station that lacks one.
Staff said the fencing does not adequately prevent access and had been identified as a problem during a DNR inspection. Another request sought approximately $30,000 to repair an unsafe treatment-plant catwalk and deteriorating air-system components.
The utility presentation also included continued work on a previously approved water-main replacement project that had been delayed while staff located the existing main.
Street Department Requests Replacement Equipment
Street department staff requested a $68,324 crack-sealing machine to replace an approximately 20-year-old unit with a failed pump that they said can no longer be replaced.
The city has been renting equipment to continue the work. Staff explained that sealing cracks helps keep water from entering pavement and causing additional damage when it freezes.
Other requests included a $17,099 zero-turn mower, a $5,397 concrete saw, a $4,840 air-conditioning replacement for the street shop and an $8,439 skid-steer attachment whose cost would be shared among the street, water and sewer departments.
Staff said the shared attachment could help clear utility access routes and reduce spending on outside mowing services.
Officials also discussed deteriorating concrete, a damaged road culvert and drainage problems that leave a park parking lot wet and slippery.
Animal control’s presentation identified a need to replace or remodel aging office space, along with approximately $10,000 for appliances, furniture and equipment. A firm construction or remodeling estimate was not presented.
Board Approves No-Cost Wastewater Assessment
The board approved a resolution authorizing an agreement for a no-cost assessment and project-development services for wastewater treatment plants.
A company representative said the assessment would examine facility data and determine whether energy performance contracting could help address longer-term infrastructure needs.
The action authorized the assessment. It did not approve construction spending on the larger improvements discussed during the budget presentations.
Resident Challenges Mayoral Term
During public comment, a resident challenged the city’s treatment of the mayor’s term of office, arguing that a 2014 voter-approved change to two-year terms should govern the timing of the next mayoral election.
The speaker said he had sought to intervene in related litigation, requested records concerning the city’s handling of the matter and urged officials to place the mayor’s office on the April 2027 ballot.
The speaker disputed the city’s handling of the term question; his allegations were presented during public comment and were not findings made by the board.
Stay connected to what’s happening in Jefferson County
The Jefferson Review delivers the local government decisions, development updates, and community stories shaping our county every Thursday and Sunday.
Don’t miss what your neighbors are talking about.
Join thousands of Jefferson County residents already reading The Jefferson Review.
Don’t miss the local government decisions, development updates, and community stories shaping our county every Thursday and Sunday.